Madison County IDA rejects $30 million tax break for Hoffman Falls Wind; developer says it will still build

News October 29, 2026 7 min read Suggest a correction

The Madison County Industrial Development Agency voted on Wednesday, October 14, 2026, to reject a payment-in-lieu-of-taxes deal for Hoffman Falls Wind, a wind farm that Liberty Renewables is building across the towns of Eaton, Fenner, Nelson and Smithfield in Madison County, WRVO Public Media reported on October 15. The request was worth about $30 million in tax breaks over 20 years, and the developer said afterward that construction will go on without them.

IDA chair Rick Bargabos said the application was never complete because the host community agreements the agency required before its public hearings were not signed, according to WRVO. The company’s attorney rejected his suggestion that Liberty Renewables had acted in bad faith. WRVO did not report a vote count or how individual board members voted, and the agency had not posted minutes of the October meeting.

Hoffman Falls Wind at a glance

The project’s basic numbers come from the company’s application to the IDA, the agency’s hearing notices and the state’s permit announcement.

  • The applicant is Hoffman Falls Wind LLC, which the application says is wholly owned by Copenhagen Infrastructure Partners Fund V, with offices at 412 W. 15th Street in New York City.
  • The IDA notices describe up to 18 wind turbines with a combined capacity of about 110 megawatts, and a cost-benefit questionnaire in the same filing lists 109.8 megawatts.
  • The plan includes an operations and maintenance building of about 7,500 square feet, plus substations, transformers and underground and overhead cabling.
  • The application puts total project costs at $438,883,691, including $143.73 million for machinery and equipment.
  • The company told the IDA the wind farm would create two permanent full-time jobs.

The application says all the land the project needs is secured, almost entirely through leases, with one parcel held under a purchase option that runs to March 2027. A list of landowners attached to the filing includes farms and families in the four towns.

What the tax deal would have done

Hoffman Falls Wind asked the agency for three kinds of exemptions, according to the application posted by the IDA. The figures below are the company’s own estimates.

  • Sales and use tax exemptions worth $15,821,702 on about $197.8 million in purchases.
  • A real property tax exemption worth $7,710,575, replaced by payments in lieu of taxes.
  • A mortgage recording tax exemption listed at $3,730,511 in one part of the application and $3,591,516 in another.

Under the proposed schedule, the payments in lieu of taxes would have started at $500,000 in the first year and climbed 2% a year to $728,405.57 in year 20, for a total of $12,148,684.75. The company estimated that the land now pays $215,453 a year in property taxes. The company acknowledged that the 20-year term departs from the IDA’s uniform tax exemption policy and said it wanted the term to match the length of its host community agreements with each town. A fixed schedule would give the towns and the company certainty, the filing argued, compared with the state tax department’s assessment model for wind projects, which it said produces fluctuating numbers.

The application also said the host community agreements would pay the towns $4,500 per megawatt each year for the life of the project, on top of the PILOT. The company said it planned to put about $50,000 a year into a local charitable fund or grant program. In the same filing, the company told the IDA the project would not be financially viable without the agency’s help.

Why the IDA said no

Bargabos told the board that the company had started construction without the tax benefits and had sent a letter saying the project would go ahead regardless of its host community agreements, WRVO reported. Those agreements had not been executed, which the IDA had made a condition before the public hearing. “They failed to execute those agreements,” Bargabos said, according to WRVO. He also suggested that Liberty used the agreements as leverage to win town support for a PILOT.

Rob Panasci, a Troy attorney with Young/Sommer LLC who is listed as the company’s lawyer on the application, answered for Liberty at the meeting. He rejected the suggestion that the company had acted in bad faith, WRVO reported.

Bargabos also spoke about the state’s role. He said local residents and town governments once backed wind projects that fit with farming, and that state law now takes away local say over where large renewable projects go, according to WRVO. Projects of 25 megawatts or more are permitted by the state Office of Renewable Energy Siting (ORES), and WRVO noted that opponents, including the group Southern Hills Wind Watch, see that process as limiting local input.

The state permit

ORES issued Hoffman Falls Wind a final siting permit in December 2025, the New York State Department of Public Service announced on December 22, 2025. The state’s description of the project differs in places from the later IDA filing.

  • The permit release describes a 100-megawatt facility with up to 24 turbines, while the 2026 IDA application lists up to 18 turbines and about 110 megawatts.
  • The developers estimated about $63 million in local investment going to the four towns, the Cazenovia and Morrisville-Eaton Central School Districts and participating landowners.
  • The release said a host community agreement was expected to pay the towns about $400,000 a year, with about $100,000 a year more for neighbors through a shared community payment program.
  • The state expected the project to be operating in 2027 and to connect to National Grid’s Fenner-Cortland 115-kilovolt line.
  • ORES received more than 135 public comments and held a public comment hearing in April, according to the release.

The full permit is filed under Case Number 23-02976 in the Department of Public Service’s document system. The release said the project meets or exceeds the requirements of Article VIII of the Public Service Law. The application to the IDA says no local special permits or variances are needed because the project was permitted through ORES.

Liberty Renewables says construction continues

Meg Lee, Liberty Renewables’ director of development, said the company was disappointed that the host towns will not get PILOT payments but is moving forward with construction, according to WRVO. The company listed what it says the four towns will still get.

  • About $1 million in electric bill savings for eligible households over 10 years.
  • At least $1 million in grants over 20 years for projects that benefit Eaton, Fenner, Nelson and Smithfield.
  • Lease income for about 50 local landowners and farmers.
  • More than 70 construction jobs, along with long-term operations jobs and support for local scholarships and historic preservation.

The state’s permit release had put construction employment at about 66 full-time jobs. When the company signed its IDA application in July 2026, it said construction had not begun, a transformer had been ordered and other major equipment would be bought in 2026 and 2027. By the October meeting, Bargabos said work was underway. Liberty is also developing wind projects in Cayuga and Cattaraugus counties, WRVO reported.

The August hearings

The IDA held public hearings on the request in each host town, according to the agency’s notices for Nelson, Fenner, Eaton and Smithfield.

  • Nelson Town Hall, 4085 Nelson Road, on August 24, 2026, at 5 p.m.
  • Fenner Town Hall, 3151 Fenner East Road, on August 24, 2026, at 6:45 p.m.
  • Eaton Town Offices, 35 Cedar Street, on August 25, 2026, at 5 p.m.
  • Smithfield Town Hall, 5255 Pleasant Valley Road, on August 25, 2026, at 6:45 p.m.

The notices said the IDA had not yet completed its environmental review of the project under state law when the hearings were scheduled. A transcript or summary of the hearings was to go to agency members.

What happens next

With the PILOT rejected, the wind farm will not get the IDA’s sales, mortgage recording or property tax exemptions. WRVO’s report did not say how the four towns, their school districts and Madison County will now assess and tax the project. Whether the host community agreements will be signed is also open; the IDA’s account and the company’s account of those agreements differ.

Written comments and questions about the IDA’s handling of the application go to executive director Kipp Hicks at the Madison County Industrial Development Agency, 3215 Seneca Turnpike, Canastota, or (315) 697-9817, according to the hearing notices. The state expects the wind farm to begin operating in 2027.

Have a tip or a correction? Send it to CNY Magazine.